status-report
Line-by-line Instructions
- Resources used this period
- Keep track of the number of hours of effort spent on this
project so that it can be tracked against the plan.
- Status Summary
- This is a one-line executive summary of the status of the project.
- Open Issues
- Link to open issues for this release in your issue tracking
tool. Group issues by type, internal milestone, or priority. These
issues are the best description of the work that the team must do
before the next release.
- Resolved Issues
- Link to resolved but unverified issues in your issue tracking
tool. This list is a description of recently completed development
fixes that must still be verified before they are known to be
correct.
- Closed Issues
- Link to recently closed issues in your issue tracking tool.
This list is the best indication of what your team has done
recently.
- Other metrics
- Track metrics such as lines of code written and test coverage to
give an indication of the amount of progress that has been made
toward stated goals.
- Detailed Status
- Use 1-4 paragraphs to briefly describe the project status. List
things that were done in this time period. Put the current work
into the context of the overall project. If help or additional
resources are needed, justify that need here.
- Upcoming Activity
- Briefly describe what the team will do next.
- Tracking to Plan
- Measure the team's progress relative to the plan. If you have
learned that the plan was incorrect, update the plan and track to
the new plan.
|